GM battery mini factory readies first test cells in Q4 2026

GM's $900 million mini factory in Warren, Michigan, will build its first LMR test cells this quarter, ahead of mass production in Tennessee in 2028.

Exterior of two connected factory buildings with glass bridge at dusk

The short version

  • GM's Battery Cell Development Center in Warren, Michigan, is a half-million-square-foot mini factory for testing how to mass-produce new battery cells.
  • Its first test cells, lithium manganese-rich (LMR) prismatic cells, are due in the fourth quarter of 2026.
  • GM puts the cost of the center and its neighboring Wallace lab at $900 million, and the mini factory tops out at about 0.5 gigawatt-hours a year.
  • Ultium Cells will mass-produce LMR cells at Spring Hill, Tennessee, with upgrades due to finish in 2028 and 500 new jobs planned.
Quick read · 1 min

GM is finishing a half-million-square-foot mini factory, the Battery Cell Development Center, on its Warren, Michigan, campus. It is not built for big volumes. Its job is to work out how to mass-produce new, cheaper battery cells before they go to full-size plants, and its first test cells are due in the fourth quarter of 2026.

This matters because the battery is the priciest part of an EV. GM's first test cells use LMR, a chemistry with little cobalt and less nickel that GM says holds a third more energy than cheap LFP cells at a similar cost.

  • Cost: $900 million for the center and the Wallace lab next door.
  • Output: up to about 0.5 gigawatt-hours a year, for testing.
  • Next: mass production at Spring Hill, Tennessee, in 2028, with 500 new jobs.

Two plain white buildings at the far end of GM’s huge Warren, Michigan, campus could decide how much your next electric car costs. Inside, GM is finishing a half-million-square-foot mini factory whose job is not to build lots of batteries, but to learn how to build cheaper ones fast. Its first test cells are due in the fourth quarter of 2026.

Why should a driver care? The battery pack is the most expensive part of an EV, making up as much as 40% of the cost of GM’s electric models. GM sells more EVs in the US than anyone except Tesla, yet most of its lineup still costs too much for many buyers. Cheaper cells are the most direct path to a cheaper car, and GM also wants cells that rely less on minerals China controls.

01

What is the GM Battery Cell Development Center?

The GM Battery Cell Development Center, or BCDC, is a low-volume battery plant that sits between the research lab and the giant factories. GM battery chief Kurt Kelty described it as the link that gets a new cell from the lab into production, using computer modeling, physical testing and small production lines together.

Here is the problem it solves. Inventing a new battery chemistry is one thing. Making hundreds of thousands of identical, safe cells from it is another, and that step has usually taken a decade or more and been done by battery makers overseas. GM wants to do it in-house, and in less time.

The center is the third step in a four-step chain. GM’s Kettering lab invents and tests chemistries one small cell at a time. The Wallace Battery Cell Innovation Center next door builds full-size cells in batches of a few dozen. The BCDC then runs real factory machinery to make thousands of cells a day. Finally, high-volume plants take over, making cells by the hundreds of thousands or millions.

Gloved hands handling a prismatic battery cell frame on a bench in a clean bay
02

How the mini factory works

The BCDC has the same kind of machines as a full plant, just fewer of them. The first building makes the electrodes, the layers inside a cell that store and release energy. Big vats mix a paste called slurry, and coating machines spread it onto thin film, with anode work on one side and cathode work on the other.

A bridge carries rolls of that coated film to the second building. There, cells are assembled, charged for the first time and tested for eight to 11 days. The upper floors hold metals, films and parts, plus a large air-handling system that keeps the rooms clean, dust-free and at a steady temperature.

Scale tells the story. At most, the center could turn out about 0.5 gigawatt-hours of cells a year, a small amount by factory standards. GM says the point is quality, not quantity. GM puts the combined cost of the BCDC and the Wallace lab at $900 million.

03

Why GM is betting on LMR battery cells

The first cells off the line will be LMR prismatic cells. LMR stands for lithium manganese-rich, a chemistry that uses very little cobalt and much less nickel than today’s premium batteries. Prismatic means a flat, rectangular hard case rather than a soft pouch.

GM says LMR packs about 33% more energy into the same space than lithium iron phosphate (LFP), the cheap chemistry that dominates in China, at about the same cost. A GM battery engineer said the cells use less than half the nickel of today’s high-nickel cells, which are about 85% nickel. LMR has a history of wearing out quickly and losing voltage, and Kelty has admitted much of the industry sees it as a long shot. GM believes it has fixed those problems, and the BCDC is where it has to prove it.

After LMR, the center will also build sodium-ion prismatic cells for grid storage, developed with the startup Peak Energy.

laboratory workspace with testing equipment for battery cells
04

The 300,000 designs GM tested on computers first

GM leans heavily on simulation before anything touches a machine. In late October, at its GM Forward event, the company said its engineers tried out more than 300,000 virtual versions of the next EV battery before any real cell was made. That took 300 million hours of processor time, which GM compares to one computer running nonstop for 34,000 years.

GM uses digital models of everything from the whole car down to atoms moving inside a cell. The company says this kind of modeling, together with the mini factory, should get new cells built and tested in about half the usual time. GM argues that is how it can keep pace with Chinese battery makers.

05

What this means for EV buyers

Nothing changes at the dealer this year. GM’s LMR cells won’t go into mass production until 2028, and the BCDC’s work now is about proving that the cells and the process hold up.

If it works, the payoff is real. Cheaper cells with more range per dollar would let GM sell EVs closer to what most people pay for a car, at a time when the average new vehicle costs about $50,000. Interest in EVs jumped this year when gas prices rose 40% after the war in Iran, mostly for cheaper models. Cells built in the US with fewer Chinese-controlled minerals could also make prices less exposed to trade fights and supply shocks.

The mass-production plan is already set. In October, Ultium Cells, GM’s joint venture with LG Energy Solution, said it will make LMR prismatic cells at its Spring Hill, Tennessee, plant near Nashville. Upgrades start later this year and should finish in 2028, adding 500 jobs to a workforce of 1,200. GM says that would make Ultium the first company in the world to produce LMR cells commercially. High-nickel cells will stay in GM’s longest-range models.

06

Quick answers

Where is GM’s Battery Cell Development Center?

It is on GM’s 710-acre technical campus in Warren, Michigan, about 15 miles north of Detroit, next to the Wallace Battery Cell Innovation Center.

When will the first test cells be made?

GM says the first LMR prismatic test cells will come off the BCDC line in the fourth quarter of 2026.

When will cars get the new LMR batteries?

Volume production is planned for 2028 at the Ultium Cells plant in Spring Hill, Tennessee.